Phase I Promethean Board Installations Complete! Projector Project Proceeds to HOW, TIM, and SHS

Year 2~Day 206 +177/366: Math - Teacher Educat...

Image by Old Shoe Woman via Flickr

We can celebrate a milestone today . . .

New Promethean boards have been installed at all Phase I campuses.

There are still boards that have been pulled from some campuses for repurposing that have not been placed yet but will be prior to the beginning of the school year.

The installation of projector systems at the secondary campuses continues. T. A. Howard will be complete tomorrow. Another crew is working at Cross Timbers. The project will move to Summit High School on Friday.

Enhanced by Zemanta
10 Comments Post a comment
  1. Therese Borden #

    Thank you for all of your hard work this summer. Tech department deserves a gold star from all of us. YEA!

    July 20, 2010
    • Thanks for the gold star! With such dedicated technicians and specialists in the Technology Development Department, forward thinking leadership of our district, ongoing cooperation among departments, and sustained commitment to developing new skills among our teachers and staff members, we think it’s shaping up to be a great year!

      July 20, 2010
  2. Karen Oates-Jackson #

    Any news on Wester’s progress? I know it was one of the campus’ that needed electrical work done. Will we have any upgrades prior to the school year beginning?
    Thanks.

    July 20, 2010
    • The good news is that the electrical work required is less extensive than we thought it might be. MISD Maintenance has done a great job of assessing the District’s needs in this area. We should have more information to share about this on Wednesday of next week.

      July 20, 2010
  3. Stacie Guerra #

    Do you know when Phase II will begin? I’m so excited that we will be receiving this technology! Thanks! :0)

    July 21, 2010
    • No, we’re not sure when Phase II will begin in terms of installation. However, Mary Lemons and the planning team have conducted walk-throughs at MHS and THS already.

      July 21, 2010
  4. Shawntee Cowan #

    Do you project that Phase II may be completed before the end of the upcoming school year? I am working on my Action Research Study for grad school and I am wondering if the use of this technology would be a possibility for research on my campus.

    July 21, 2010
  5. Lovey Turner #

    Just wondering if the boards and projectors were installed in the portables at JL Boren. All 4th grade classes are in portables and we are excited about receiving the technology upgrade:)

    July 21, 2010
    • The projector system and Promethean board installations are taking place at different campuses. Now that the installations of boards are complete within the elementary school buildings, the projector system installers can begin their work at those campuses once they finish the Phase I secondary campuses. Portables or temporary buildings that house eligible classes will be equipped with Promethean boards, most of which will be repurposed from other classrooms in the District.

      July 21, 2010
  6. Melissa #

    I’ve been up to school this week to see the boards! I’m so excited to have this resource in my room! My teacher-friends from other districts are so jealous! Can’t wait to start using it every day 🙂

    July 22, 2010

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s